Реферат по предмету "Иностранный язык"


Construction Project Observations Essay Research Paper Project

Construction Project Observations Essay, Research Paper

Project Description

After several months of planning and design, excavation for the new ACES library on the University of Illinois campus began in May 1999. The project is sponsored and will be owned by the Board of Trustees for the University of Illinois. Six separate contractors are working together under one general contractor. The project, which began in May of 1999, is scheduled to be completed by February 2001. Through informal interviews with Charles O. Pickar we learned that the project is 4-5 weeks behind schedule. Pending weather conditions 25 to 35 workers usually present on site. The typical workday can run between 6:30am and depending on deadlines can last until 9-10pm. As of the third week in January 2000, the concrete foundation and the steel framework for the five-story structure, with the exception of the roof, were intact. The appendix of this report contains photographs of observed procedures and site materials.

Observed Operations

January 27, 2000

On the morning of January 27, two massive 18-wheel trucks carrying various shapes and sizes of steel beams were unloaded on site. It took almost two hours to unload each truck. A crane approximately 200 ft. high was used to move the steel from the truck onto wooden planks on the ground. The steel was separated by shape, and by using the quite large reaching span of the crane, the workers were able to deliver the beams directly from the truck to their appropriate sides of the site. This operation involved a six-man crew. Two men connected the hooks from the crane onto the steel. Two men guided the steel onto the planks on the ground. Two men took turns operating the crane. This process was very time consuming due to the amount of steel needed to be lifted entirely over the five story structure to the other side of the site, and due to what seemed to be a lack of experience of the rigging crew. It took them a very long time to make the connections on each beam, and check for security. These factors may have influenced the unloading time taken that morning.

As these trucks were being unloaded, another crew of men worked in the basement. No equipment was being placed at that time, but people were hauling down tools and what looked to be some sort of electrical cords. Perhaps they were working to install some piece of equipment already lowered down there, or maybe they were moving already dropped equipment away from the opening in the floor to make room for more to be lowered.

January 28, 2000

Installation of metal decking floor supports began on Friday, January 28. By the early afternoon, the level between the first and second stories was nearly complete. There were some openings left, mostly on the south side of the building, which will serve as stairways and elevator shafts. The center of the building also lacked decking, and judging by the design drawings, this section was left opened for a skylight, which will cover the apex of the roof upon completion. The decking between the second and third stories was about half installed by 3:00pm. A two-man team of welders worked to secure the union of the decking to the steel framework as each section was placed. Special protective masks and eye shields were used to ensure no damage was done to the eyesight of the welders during this process. Decking sheets lay in bundles on the beams between the third and fourth floors, awaiting installation. Upon completion, safety inspectors will come out to the site to check the torque on the bolts and the security of the welds. The sheets were placed connecting to studs sticking upward from the steel framework. The outside beams were such that they remained higher vertically than the steel reinforcement going in. This design allows for concrete to be poured over the decking without it spilling over the sides of the building. This entire process, including the welders, men placing the decking, and one man who was sweeping debris from the recently installed supports, entailed a crew of seven men. Due to the afternoon increase in snowfall, and the increase of wind, the crew began covering their equipment with plastic tarps and prepared to quit for the day at around 3:30pm.

January 31, 2000

No work was done on this site during the weekend, but activity began again early Monday morning, January 31. The 200 ft. crane lifted three of six large steel beams onto the top mid section of the building, which will eventually support a roof that slants upward from the fifth story to the top of the skylight. The crane was attached to the top of the beams and lowered them vertically onto the structure. Each beam had three small steel ledges, which stuck out horizontally near the top, and were designed to support piping that will run above the ceiling. Two men waited, standing on the fifth story framework to secure the beams in place once the crane had placed them. These men drove spikes into holes in the beam to anchor them to the structure. Both wore safety harnesses to ensure that they wouldn’t lose their balance while hammering the beams in place. By noon, three beams were set and secured.

At the same time the mid section steel erection was taking place, another crew worked to pump concrete into the basement of the structure. A concrete mixing truck was backed up to a pump truck, which had a long arm reaching over into a hole in the concrete foundation. Two men watched to ensure that the materials flowed smoothly from the mix truck to the pump truck. Two other men stood near the end of the long arm of the pump truck, making sure the concrete reached its final destination. Perhaps this meant that all the necessary equipment for that area of the basement was installed, so the flooring was ready to be set.

February 1, 2000

The afternoon of February 1 was exceptionally slow. The blowing snow forced the ironworkers to abandon their placement of any additional decking. Storage of steel beams is adjacent to the construction site organized by type and size. The steel beams are the main materials being used during this phase of the construction and are closest to the workers for convenience and efficiency. A few men worked down below in the basement, but no surface activity was happening. This delay no doubt forced the schedule back for the completed installation of flooring reinforcement, and in effect caused delays for pouring the floors. This leads to a domino effect, pushing back the completion dates of every other part of the process dependent on the flooring being secured and the basement equipment being installed, which in essence, is every other part of the project.

February 2, 2000

While observing construction on Wednesday there were approximately eight workers operating the machinery and working with the steel materials. Two men were on the ground going through the piles and hooking up pieces of steel to the crane. The crane operator would move the beams away from the steel beam piles to other workers who would bolt the beams into position. You could observe today that workers have begun to lay steel sheets on the second story that has already been assembled. This steel is placed over the floor trusses and then bolted down. Within in the site there was a concrete bucket for the crane, which will most likely be used to pour concrete for the individual floors. They can only lay the steel and pour one floor at a time or the steel from the above floor will be in the way of getting the concrete bucket through. Within the construction site were piles of wire mesh and reinforcement bars. This probably will be used as reinforcement for the concrete floors. Safety remained important through out this phase of construction and was demonstrated through rails, which were placed around the floors and during the systematic processes used during the hooking and moving of individual steam beams. There were four electricity trucks present today and they appeared to be digging the power supply line to the building. Three men and a digging machine conducted the digging of the power supply line.

February 3, 2000

On the afternoon of Thursday February 3, the site, just by looking, didn’t seem to have made any progress from the previous day. However, workers were going down into the basement. Due to safety concerns, visitors were not allowed down below the structure. In order to find out what was happening, discussions with engineer Charles Pickar of Sebesta Blomberg and Associates, Inc. were used to fill in the blanks. He explained that the electricians and pipe fitters were working in the basement running conduit and laying pipe. As soon as they were done, the fire suppression people could get down there to spray the piping. They were working to get the necessary wiring complete so more equipment could be lowered and hooked up as soon as weather allowed. As for now, the site was supplied power through a shed, which was tapped into a near by permanent power supply. Some parts of the basement were already filled in, but one main hole was left opened to get the transformers and air handling units down. Also in the basement, men were laying diamond supports on the steel footings to prevent cracking in the concrete foundation from the stress of the columns. These processes all continued underground through the afternoon.

February 4, 2000

The snow and wind on the afternoon of Friday, February 4 again forced the ironworkers to abandon lying any additional floor decking. A crew of three men prepared to drop a transformer into the basement. The crane was extendible and looked to be at about 100 ft. The riggers took their time securing the connection, but due to wind, never attempted to move the unit. Mr. Pickar later explained that this particular type of crane is not very stable. If the load sways while being transferred, there is a great possibility that it will flip. Keeping in mind operator safety, as well as the safety of nearby crewmembers, risks are just too great to attempt transfer today. Tarps covered the transistors and the crane lowered and folded up. Mr. Pickar also mentioned that a late delivery of hangers for the basement earlier in the project was already pushing everything behind schedule. The weather problems further added to those delays.

Looking at the architectural drawings covering several tables in the construction office, it was noted that there will eventually be a tunnel running underground out the north end of the library and into nearby buildings. Several revisions had to be made on these drawings, especially in regards to the structure itself, to modify the ideas of the designer with the feasibility of engineering. Sebesta Blomberg, which is primarily an engineering company, did most of the modifications. There were almost 1000 pages just of architectural design and several other books of drawings, such as electrical and mechanical work, which were equally as thick. These all seemed to be labeled in an efficient manner to assure that pages could be easily located. This is especially useful when phone calls come in and someone needs to know something like a dimension on a certain machine in a certain room. People with identical books can easily direct another over the phone to a specific page. Depending on the type of work it entails, specific areas within each book are easy to find just by reading the markings on the bottom corners of the pages.

Safety Issues

In reference to safety issues other than the specific situations mentioned before, it was noted that anyone entering the site was required to wear a hard hat as well as construction boots. Every worker wore thick gloves and some wore safety eyeglasses. All crane operations were taken slowly and all ironwork was called off at the first signs of slickness or dangerous winds. Anyone operating machinery, such as the welders or crane operators were trained and certified prior to working. All visitors were required to sign in and out to alert those in charge as to who was on site in case of an emergency. The construction office bookcase was filled with safety manuals, OSHA guides, project management workbooks, structural welding guides etc. All the drawings contained clear markings referring to placement of safety equipment, such as fire alarm and hose reels. Safety inspection was accounted for in the scheduling process and any sort of risks taken very seriously by all members of the working and management crew.

Construction Observation Conclusions

In conclusion, this construction project reflects a complex system of seemingly unrelated activities, which in actuality are crucially dependent on one another. The timing of the start and finish of every little detail is scheduled so that it fits in the order necessary to complete the project in the most efficient way. Advanced planning, foresight, and experience are used to ensure processes are done in the right order. An example of this is the basement project. The design must call for a section of flooring to be left out. Hangers have to go in before wire and pipes, which have to go in before machinery, which has to go in before fire safety equipment and inspection, which has to be done before the floor gets closed up. Each link in the chain is essential. Delays can easily build up fast if one link can’t finish the job. It’s the responsibility of the construction manager to ensure that materials get there on time and that workers have the qualifications and tools necessary to complete the task. The construction manager must keep an eye on all aspects of the project, paying special attention to safety codes and restrictions, and understand the interdependence of each days events in order to avoid delays, maintain a safe working environment, and keep the schedule moving smoothly until every final detail has reached completion.




Не сдавайте скачаную работу преподавателю!
Данный реферат Вы можете использовать для подготовки курсовых проектов.

Поделись с друзьями, за репост + 100 мильонов к студенческой карме :

Пишем реферат самостоятельно:
! Как писать рефераты
Практические рекомендации по написанию студенческих рефератов.
! План реферата Краткий список разделов, отражающий структура и порядок работы над будующим рефератом.
! Введение реферата Вводная часть работы, в которой отражается цель и обозначается список задач.
! Заключение реферата В заключении подводятся итоги, описывается была ли достигнута поставленная цель, каковы результаты.
! Оформление рефератов Методические рекомендации по грамотному оформлению работы по ГОСТ.

Читайте также:
Виды рефератов Какими бывают рефераты по своему назначению и структуре.

Сейчас смотрят :

Реферат Охрана поверхностных вод
Реферат Использование метода гештальт-терапии в социально-психологической реабилитации военнослужащих, получивших ранения
Реферат Эффективность технологии социальной работы с семьями детей с ограниченными возможностями здоровь
Реферат О современном статусе испанского языка в США
Реферат Мэрилин Монро жизнь смерть творчество
Реферат Parts Essay Research Paper Parts Pieces and
Реферат Cloning 2 Essay Research Paper Extinction to
Реферат Environmental Racism Essay Research Paper There is
Реферат Матрицы, Метод Гаусса
Реферат Madam Bovary Essay Research Paper Chapters 16
Реферат А. Б. Давидсон новые отношения бывшей метрополии с бывшими колониями //Россия и Британия. Вып. Вмире английской истории. М.: Наука, 2003. с. 121129
Реферат Лидерство и типы лидерства
Реферат Состояние и перспективы развития страхования в России
Реферат Специфика дальневосточных транспортных узлов на примере портов Восточного и Владивостока
Реферат «Современный беспроводной интернет»